Arbitration clause Default proceedings Interest Contract concerning a project for the development of a new technology for producing impermeable leathers Reimbursement of an advance payment


Sumário

Judgment of the Court of First Instance (Fourth Chamber) of 12 July 2007.
Commission of the European Communities v Efrosyni Alexiadou.
Arbitration clause - Contract concerning a project for the development of a new technology for producing impermeable leathers - Reimbursement of an advance payment - Interest - Default proceedings.
Case T-312/05.


Texto da decisão





Judgment of the Court of First Instance (Fourth Chamber) of 12 July 2007 – Commission v Alexiadou

(Case T-312/05)

Arbitration clause – Contract concerning a project for the development of a new technology for producing impermeable leathers – Reimbursement of an advance payment – Interest – Default proceedings

1. Procedure – Reference to the Court pursuant to an arbitration clause (Art. 238 EC) (see paras 33-35)

2. Procedure – Application initiating proceedings – Formal requirements – Summary statement of pleas (Rules of Procedure of the Court of First Instance, Art. 44(1)) (see para. 37)

Re:

APPLICATION brought by the Commission under Article 238 EC with a view to securing repayment of an advance made to the defendant in the context of a contract concerning a project for the development of technology for producing impermeable leathers (contract G1ST-CT-2002-50227).

Operative part

The Court:

Dismisses the application;